Status of New Baiyappanhalli Terminal:
- As on 24th Feb PF 1 & 2 Concrete & tracks work is completed alongside Electric pole work is going on at a brisk pace.
- There will be 2 Subways connecting all 7 Platforms for the ease movement of Passengers.
- Under 1st Phase 3 platforms will be ready by July/Aug 2019
Next...
more... phase by March 2020
- As of now, there are 3 pit lines & 4 Stabling Lines
- Numbers in Place (Includes 2 phases)
No.of Platforms: 07
Pitline: 04
Stabling Line: 05
One sick line
Here is the video Link:
click here Date: 24th Feb 2019