Got incomplete info from WR HQ about Udhna Jalgaon Doubling plus Electrification #UDNJLdoubling
.
.
Grievance Description : Dear Sir, Please provide details of current status of electrification and Doubling of Udhna Jalgaon section. Also please tell by what time it will be completed and Plan of making Terminal of Udhna Junction and when it will completed
Current...
more... Status : CASE CLOSED
Date of Action : 03 Sep 2015
Details : Udhna Jalgaon doubling project (306.93 Km) :- 85 Km - Vyara-Ukaisongarh (20 Kms.) , Amalner-Dharangaon (25 Kms.) Ukaisongarh-Chinchpada (40 Kms.) Sections have been commissioned. 74 Km - Bardoli-Vyara (29 Km.), Khandbara-Bhadwad (7 Km.), Dhekvad-Nandurbar(8 Km) , Chawalkhede-Girna (18 Km.) , Dharangaon-Chawalkhede (07 Km.) Girana Bridge-JL (5 Km): Track linking has been completed with service rail. TRR with FB welded 20 rail panel (welded in workshop), Ballast insertion, dressing boxing completed. Electrification work is in progress, section will be offered for CRS inspection on completion of electrification signaling work. 70 Km. - Chalthan-Bardoli (16 Kms.), Chinchpada-Khandbara (18 Kms.), Bhadwad-Dhekvad (8 Km) Amalner-Nardana (28 Kms.) : Track linking has been completed with sevice rails during 2014-15. TRR with FB welded 20 rail panel (welded in workshop), Ballast insertion, dressing , boxing , TTM tamping and other misc. works are in progress. 65 Km – Udhna-Chalthan (11 Kms.), Na