Big war of words between Reel Minister & Leer MP.
Vaishnav vs Gokhale regarding VB Sleeper Trains.
Here are the tweets & My take on this after doing simple maths.
See here Rs. 58000 Crore/3200 Coaches = 18.125 Crore/Coach & Rs. 58000 Crore/3192 coaches = 18.17 Crore/Coach. Now 3192 Coaches X 18.125 Crore/Coach = Rs. 57855 Crores. Hence difference is...
more... = Rs. 58000 Crore - Rs. 57855 Crore = 145 Crore herfer. Cost increment from Order 1 to Order 2 = 145 Crore/3192 = Rs. 4,54,260.65 per coach.
Note that Order 1 was 200 VB Sleeper Trainsets having 16 coaches & Order 2 is 133 VB Sleeper Trainsets having 24 coaches. Order1 - Order2 is 8 coach less in total. Rs. 145 Crore/8 Coaches = Rs. 18.125 Crore/ Coach.
So IR paying Rs. 145 Crore more for Order 2 as the Total Value of Order is at Rs. 58000 Crore.
please wait...Translate to EnglishBig war of words between the Rail Minister and the Lok Sabha MP.
Vaishnav vs Gokhale regarding VB Sleeper Trains.
Here are the tweets and my take on this after doing simple math.
See here Rs. 58,000 Crore/3200 Coaches = 18.125 Crore/Coach & Rs. 58,000 Crore/3192 coaches = 18.17 Crore/Coach. Now 3192 Coaches X 18.125 Crore/Coach = Rs. 57,855 Crores. Hence the difference is = Rs. 58,000 Crore - Rs. 57,855 Crore = 145 Crore. Cost increment from Order 1 to Order 2 = 145 Crore/3192 = Rs. 4,54,260.65 per coach.
Note that Order 1 was 200 VB Sleeper Trainsets having 16 coaches & Order 2 is 133 VB Sleeper Trainsets having 24 coaches. Order 1 - Order 2 is 8 coaches less in total. Rs. 145 Crore/8 Coaches = Rs. 18.125 Crore/ Coach.
So IR is paying Rs. 145 Crore more for Order 2 as the Total Value of Order is at Rs. 58,000 Crore.