Central Budget Allocations for RAMESWARAM DHANUSHKODI RAILWAY LINE TILL DATE.
2019 = 1 lakh
2020 = 3 crores
2021 = 75 crores
2022...
more... = 59 crores
2023 = 444 crores
2024 = 1 crore
Total 582 crores allocated outoff total 733 crores. (Initially planned as 208.7 crores later revised as 733 crores due to the geographical construction work)
Forest department land = 28.6 hectares
State Government land = 43.81 hectares
Private land = 3.66 hectares...
To be acquired by Southern Railway for the construction of this line.
So far, no such allocation of money has been found in Tamil Nadu/Southern Railway zone for a single railway stretch. But 0 works were started till date.
please wait...Translate to EnglishThe money allocated for RAMESWARAM DHANUSHKODI RAILWAY LINE till now are:
2019 = $100,000
2020 = $3 million
2021 = $75 million
2022 = $59 million
2023 = $444 million
2024 = $1 million
Total of $582 million has been allocated out of the total $733 million planned because of more construction costs.
They need 28.6 hectares from the forest department, 43.81 hectares from the state government, and 3.66 hectares of private land to build it. Southern Railway gonna get it.
Even though they haven't started working yet, this railway stretch is costing a lot and breaking records!