Rail Connectivity embraces a new era for Manipur!
🚉Jiribam-Imphal Rail Line Project(110.93 km)
📈Overall Progress: 93.30%
...
more... 🌉Bridge Works Completed
- Major: 5/11
- Minor: 101/137
-ROB/RUB: 8/16
⛰️Tunneling Work: 59.11Km/61.32Km
*As on 16th March 2023
#RailInfra4ManipurSource: MOR Twitter Handle