Statutory Inspection of RE works followed by speed trial at full sectional speed(110Kmph) in Rajkot-Jetalsar(74.5RKM/84.4TKM)single line section of Rajkot and Bhavnagar Divisions of WR completed successfully. With this,total commissioning by CORE during2022-23 is2037.2RKM/2756.5TKM.