Latest updates on PUNE-MIRAJ (280 KM) Doubling updates:
- Central Rly length: 280 km
Two block sections (13.68km) already commissioned in June 2019.
Pune-Alandi section (23.22 Kms) commissioned on 03.02.2020.
Daundaj-Valha...
more... section (8.52 Kms) CRS Insp. done on 22.10.20 & commissioned on 03.11.2020
- Further work of EW, Major & Minor bridge works, Const. of S/Bldg. & R/Bldg. PF, FOBs & other misc. civil works & P.way works are in progress entire PA-MRJ section at various stretches
- However, work was delayed due to COVID 19. 75 Ha of land is still not yet handed by State Govt. Also, the land owners are not allowing to work on Rly. land.
In SWR Limits between Londa-Miraj (188km)
46kms stretch between Ghataprabha-Kudachi section doubled & commissioned for traffic
- Belgavi to Khanapur side track work to be started by this month end (Land levelling is completed)
- In remaining section work is in progress
#InfraUpdates #IndianRailways