Shoranur Calicut Railway Electrification updates:-
*** Poles erected and concreted around 90% upto Calicut RS
*** Overhead work are completed, Upto Kallai RS, except Panniyankara Railway Gate area
*** Both the lines are electrified upto Meenchantha.
***...
more... Day before yesterday started prelim and signal work of lifting the 1st ROB.
Pic #1 Overhead work completed upto Kallai RS - Left side is the proposal for Panniyankara FLYOVER, work will done by DMRC
Pic #2 Electrification and overhead work reached Kallai RS
Pic # 3 & 4, 5, Calicut RS, Poles concreted