CRS has issued final authorisation for Yelahanka-Makalidurga double line section (Total Length: 35.97km)
Yelahanka - Oddarahalli = 90Kmph
Oddarahalli - Makalidurga = 75Kmph
Passenger...
more... loops 15Kmph
In future PCE/SWR can authorise the sectional speed upto 110kmph (YNK-ORH) & 80kmph (ORH-MKL)
Makalidurga-Devarpalle (36kms) was commissioned on April 2019