Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
Forum Super Search
 ↓ 
×
HashTag:
Freq Contact:
Member:
Posting Date From:
Posting Date To:
Blog Category:
Train Type:
Train:
Station:
Pic/Vid:   FmT Pic:   FmT Video:
Sort by: Date:     Word Count:     Popularity:     
Public:    Pvt: Monitor:    Topics:    

Search
  Go  
dark modesite support
 
Sun Sep 29 22:27:04 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
RailCal Android App
RailCal iPhone App
Post PNRPost BlogAdvanced Search
Filters:

Page#    54 Blog Entries  <<prev  next>>
Info Update
12858 views
5

Dec 02 2023 (09:59)   NGP/Nagpur Junction (8 PFs)
Exynos9611~
Exynos9611~   24936 blog posts
Entry# 5898974            Tags  
1 compliments
Useful
#Admin #Moderator Source Cr X Handle

#CRInfraUpdates
Nagpur station major upgradation redevelopment work-
Cost- 487.77 Crores
...
more...

A) In progress works-
➡️Basement slab 50% completed. Balance work in progress
➡️Ground level slab shuttering work in progress
➡️Excavation & Foundation work in progress

B) Completed works-
✅West Side cable shifting
✅Soil investigation
✅Site lab commissioning
✅Batching plant installation
✅East Side utility shifting
✅New entry/exit for diversion of traffic
✅Parking area shifting
✅Wheel washing unit installation

CR is committed for gradual improvement of amenities for our passengers.

Translate to English
Translate to Hindi
Info Update
17295 views
6

Dec 01 2023 (09:31)   KYN/Kalyan Junction (8 PFs)
Exynos9611~
Exynos9611~   24936 blog posts
Entry# 5898107            Tags  
3 compliments
Great Useful Useful
#Admin #Moderator Source Cr X Handle

#CRInfraUpdates
🔶Kalyan- Segregation of long distance and suburban Traffic and unification of Goods Yard (Part of MUTP 3A project).
Mumbai div.
💰Cost
...
more...
– 812.97 Cr.

🔸Scope of Works-
▪️Passengers Platform faces for 6 new platforms of 620 mtr Length each.
▪️Deck Slab Covering Entire Platform area.
▪️Reception and Dispatch lines for Goods operation in proposed Goods Yard with facility of reception and dispatch towards Kasara and Karjat direction with simultaneous Reception and dispatch facility on each side.
▪️Shunting neck of full length each at Igatpuri and CSMT end
▪️Mechanical Examination facilities on two lines.
▪️Improvement of Goods shed with modification to its connectivity.
▪️Circulating area between passengers and Goods Yard.
▪️One Road Over Bridge parallel to Patri Pull Road Over Bridge (ROB) with landing Towards proposed Station Building and circulating area.
▪️Provision of 3 New Foot Over Bridge (FOB) connecting Existing Platforms to Proposed Platforms & Beyond and Service Buildings.

🔷In Progress works:
▪️Relocation of Affected Service Buildings & Quarters Under Finalization.
▪️Tender for earthwork and minor bridges has been awarded.
▪️15 old goods lines under dismantling process and 70% of dismantling work completed.
▪️Tender for track work processed.
▪️Drains, boundary wall, earthwork in progress.

🔷Entire project is aimed at segregation of long distance and suburban local trains to improve mobility.

Translate to English
Translate to Hindi

1 Public Posts - Sat Dec 02, 2023
Info Update
10396 views
3

Nov 28 2023 (13:58)  
Exynos9611~
Exynos9611~   24936 blog posts
Entry# 5895806              
2 compliments
Useful Useful
#Admin #Moderator Source Cr X Handle

#CRInfraUpdates
🔘Baramati-Lonand via Phaltan – New line
💰 Cost- ₹ 736.44 Cr.
💰
...
more...
Expenditure till date- 512.81 Cr.

🟢Overall Physical Progress- 50%
🔘Length- 64.30 Km.
🔘Length commissioned- 25.98 Km (Lonand –Phaltan)
🔘Remaining- 38.32 Km (Phaltan – Baramati )
🔘Land acquisition completed- 173.16/237.93 Hectare (72.68%)

A) Completed Sections:25.98 km
🔘Lonand -Phaltan- 25.98 km (40.44%)

B) In Progress Sections- 38.32 km (59.64%)
🔘Phaltan- Malewadi- 9.68 km
🔘Malewadi- Katphal- 28.64 km

🔴Completion of this new line will improve connectivity of this region.

🔘Progress of doubling/3rd/4th lines all over Central Railway’s 5 divisions-
🔘CR has completed 147.77 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date.

Translate to English
Translate to Hindi
Info Update
48312 views
4

Nov 26 2023 (08:55)   PDI/Palasdhari (4 PFs)
Exynos9611~
Exynos9611~   24936 blog posts
Entry# 5893854            Tags  
2 compliments
Useful Great
#Admin #Moderator Source Cr X Handle

#CRInfraUpdates
✳️ Karjat-Extension of yard line connecting UP yard to Karjat – Panvel line and 4th line between Karjat - Palasdhari.
💲Cost – 74.53
...
more...
Cr.
✳️Overall Physical Progress – 60%
✳️ Scope of work-
➡️Increase in length of EMU stabling line no. 1, 2 & 3.
➡️Increase in length of Reception and Dispatch line No. 2,3,4,5 & 6.
➡️Provision of one new Reception and Dispatch line No. 7
➡️Segregation of Karjat -Khopoli line from Khopoli- Lonavala main line.
➡️Provision of Foot Over Bridge (FOB) at Kalyan end & Lonavala end.
➡️4th line between Karjat and Palasdhari.

✳️Completed works-
➡️Extension of 8 minor bridges have been completed.
➡️Contract for earthwork has been awarded
➡️Ballast supply has been completed.
➡️Earthwork of Reception and Dispatch lines completed.
➡️Work of stabling siding no.3 completed.
➡️Work of relocation of 2 stabling line completed.
➡️Foot Over Bridge at Lonavala end completed & Commissioned.
➡️Indoor wiring completed and Outdoor wiring work 80% completed.

✳️Work In Progress –
➡️Work of Foot Over Bridge is in progress at CSMT end
➡️Earthwork for Reception & dispatch line no. 7 work is in progress.
➡️Track work of Palasdhari line is in progress.
➡️Work of siding no. 1 is near completion.
➡️Signaling wiring Testing in progress.

🛑Completion of this work will improve mobility of trains in Karjat yard and Lonavala-Palasdhari Karjat Section.
Karjat-Extension of yard line connecting UP yard to Karjat – Panvel line and 4th line between Karjat - Palasdhari.

Translate to English
Translate to Hindi
Info Update
12070 views
5

Nov 25 2023 (09:46)   KSRA/Kasara (4 PFs)
Exynos9611~
Exynos9611~   24936 blog posts
Entry# 5892961            Tags  
1 compliments
Useful
#Admin #Moderator Source Cr X Handle

#CRInfraUpdates
✳️ Kasara- yard modification with extension of yard lines.
Mumbai div.
💲Cost
...
more...
– 19.99 Cr.
✳️ Overall Physical Progress – 78%

✳️ Scope of work-
➡️ Down Yard- Increase in length of reception & dispatch lines of down yard line no 1, 2, 3 upto 844 mtr.
➡️ Extension and widening of PF No. 1 & 2.
➡️ Increase in length of reception and dispatch lines of UP yard line no 4, 5, 6.
➡️ Dismantling and Reconstruction of ROB (Road over bridge)

✳️ Completed works-
➡️ Platform Covershed work completed for 124mtr (on Igatpuri end), 144 mtr (on CSMT end )
➡️ Launching of purlins completed.
➡️ The work of micro piling & pile caps in approaches is completed.

✳️ Work In Progress –
➡️ Dismantling and reconstruction of Road Over Bridge (ROB).
➡️ Extension and widening of Platform.
➡️ Micro Pile construction for earth retention.
➡️ Excavation is in progress for abutments.

🛑Completion of this work will improve mobility of trains in Kasara to Igatpuri section.

Translate to English
Translate to Hindi
Page#    54 Blog Entries  <<prev  next>>

Travel SAFE

1. RailFanning does NOT MEAN dangerous pics/videos.
2. Doorplating pics/youtube videos are strictly FORBIDDEN in IRI.
3. Take plenty of food pics and other safe pics.
4. Write human interest narratives to make the pics interesting.
5. Enjoy blogging and travelling SAFELY.

REMEMBER: YOUR LIFE is the most precious thing, NOT RailFanning.

Leading Polls

5383447 ★★★ 145jishnuthakur12301^...
3247625 ★★★ 134~
2308508 ★★★ 38Yantravinyas
3368675 ★★★ 397mr.train_wala~

Rail News

New Trains

Site Announcements

  • Entry# 5648027
    Mar 01 2023 (12:44AM)


    In response to past confusions with Train/Station updates and resulting fights and controversies, the following clear and objective guidelines are being issued, with no room for any arguments or debates about validity. Also, included, some other changes with respect to Ratings. 1. All Red Ratings will require further explanation. Red Ratings won't...
  • Entry# 5388512
    Jun 24 2022 (08:45AM)


    As announced previously, there are a few changes coming to IRI user accounts, based on past practices. 1. As before, you will be able to quickly DELETE your IRI User account at ANY time. However, the menu option for this was hidden in the profile page, and could not easily be located....
  • Entry# 5148000
    Nov 29 2021 (06:40AM)


    A new feature will be released soon, whereby you can follow blogs tagged with specific Trains & Stations. If you have already posted blogs tagged with some Train/Station, then you will be set to automatically follow that Train/Station. Thereafter, any future news/blogs tagged with those Trains/Stations will be marked to your...
  • Entry# 5093784
    Oct 13 2021 (07:04AM)


    These days, every other day, we are getting requests from members to allow email login to their FB-based IRI account. 10 years ago, we had given the option for users to login through FaceBook - in retrospect, this was a mistake. These days, apparently, users are quitting FaceBook in droves because...
  • Entry# 4906979
    Mar 14 2021 (01:12AM)


    Followup to: Fmt Changes The new version of FmT 2.0 will soon be here - in about 2 weeks. As detailed in the previous announcement, many of the old FmT features like Train TT, Speedometer, Geo Location, etc. will be REMOVED. It will be a bare-bones simple app, focused on trip blogging. It...
  • Entry# 4898771
    Mar 06 2021 (10:33PM)


    There are some changes coming to FMT. Many of the features of FMT, like station arrival, TT, speed, geo, passing times, station time, etc. are ALREADY available in OTHER railway apps. So all of these features will be REMOVED. We'll have ONLY BLOGGING - quick upload of pics/videos/audio, etc. You may attach...
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy